Phase 1 | On Going |
Commissioning Date | Expected time of completion in month of November 2016 |
Owner | Capturesolar Energy Limited |
Financed By | PG Concept solution & Innovations Limited ( Cyprus ) |
EPC | DanSolar ( Denmark ) |
Project Location | Village NIRVI-NHAVRA District Pune. |
Project Size | 30 MWp |
Land | 100 Acres |
Sub Station | Baramati- Bhigwan 220 KV line |
Module | Mono Crestline PV Panels |
Longitude | 74 21’57″E |
Latitude | 18 38’’22.″N |
Phase 2 | On Going |
Commissioning Date | Expected time of completion in month of December 2016 |
Owner | Capturesolar Energy Limited |
Financed By | |
EPC | |
Project Location | Village Swami Chincholi, Taluka Daund, District Pune. |
Project Size | 80 MWp |
Land | 60 Hectors |
Sub Station | Baramati- Bhigwan 220 KV line |
Module | Mono Crestline PV Panels |
Longitude | 74 43’10.29″E |
Latitude | 18 18’24.85″N |
Phase 3 | On Going |
Commissioning Date | Expected time of completion in month of January 2017 |
Owner | Capturesolar Energy Limited |
Financed By | |
EPC | |
Project Location | Village Madanwadi, District Pune. |
Project Size | 70 MWp |
Land | 60 Hectors |
Sub Station | Baramati- Bhigwan 220 KV line |
Module | Mono Crestline PV Panels |
Longitude | 74 43’10.29″E |
Latitude | 18 18’24.85″N |
Phase 4 | In planning |
Commissioning Date | Expected time of completion in month of March 2017 |
Owner | Capturesolar Energy Limited |
Financed By | |
EPC | |
Project Location | Village Baramati-Bhigwan , District Pune. |
Project Size | 90 MWp |
Land | 100 Hectors |
Sub Station | Baramati- Bhigwan 220 KV line |
Module | |
Longitude | 74 43’10.29″E |
Latitude | 18 18’24.85″N |
Phase 5 | In Planning |
Commissioning Date | Expected time of commissioning in month of |
Owner | Capturesolar Pvt Ltd |
Financed By | |
EPC | |
Project Location | Village Swami Chincholi, Taluka Daund, District Pune. |
Project Size | 10 MWp |
Land | 20 Hectors |
Sub Station |
Baramati- Bhigwan 220 KV line |
Module | |
Longitude |
74 43’10.29″E |
Latitude |
18 18’24.85″N |